General Plan Update Public Hearings
Planning Commission - Board of Supervisors
Planning Commission
November & December 2009
In November and
December of 2009, Initiated hearings on the General Plan Update Draft
Text, Land Use Maps. Road Network, Community Plans, Implementation
Plan and Conservation Subdivision Program. The Hearings were on
November 6, 19 & 20 and December 4th, 2009
February 19, and March 12, 2010
The Hearings on
the General Plan Update were continued on February 19th and March 12,
and issues were discussed through a series of Fact Sheets included in
the staff report.
April 16, 2010
At the conclusion of the Planning
Commission Hearing on April 16, 2010 the Planning Commission
Recommended approval of the General Plan Update to the Board of
Supervisors, with the direction for staff to prepare a Transfer of
Development Rights Program and bring it back to the Planning
Commission prior to the Board of Supervisors. Summaries of Each of the
Planning Commission Hearings up from November 6, 2009 to April 16, 2010.
July 9 & August 20, 2010
Presented the Zoning
Ordinance Consistency Review changes to individual properties, as well
as revisions to the Zoning Ordinance, Subdivision Ordinance, and
Resource Protection Ordinance to ensure consistency with the General
Plan Update. Also presented at this hearing was the draft Transfer of
Development Rights Program Working Concept, directed to be developed
by the Planning Commission on April 16, 2010. This page also contains
the materials that were presented to the Planning Commission on August
20, 2010.
Board of Supervisors
July 23, 2008
Staff provided a project update to
the Board of Supervisors on July 23, 2008. The update includes a
report on the progress to date and highlights key issues that staff
has identified relating to the completion of the project. At the
update hearing, the Board of Supervisors directed staff to remove a
Specific Plan from the Valley Center Referral Map. This action
resulted in a one month delay on some near term project deadlines,
however the project remains on the overall schedule for completion in
Fall 2010.
May 13, 2009
Staff provided a project update to
the Board of Supervisors on May 13, 2009. The update included a
report on the progress to date and highlights key issues that staff
has identified relating to the completion of the project.
October 20, November 10, December 8, 2010
The
General Plan Update initiated hearings at the Board of Supervisors on
October 20, which was continued to November 10 and December 8, 2010.
After following nine hearings that were held by the San Diego County
Planning Commission from Nov. 6, 2009 through August 20, 2010. The
Commission made its final recommendations for approval of the General
Plan Update Aug. 20. In total, the Board heard approximately 19
organized presentations and from 172 individuals. Following public
testimony, the Board discussed the project and directed staff to
review issues raised during the hearings, including property-specific
requests, and return to the continued hearing Feb. 9, 2011, with
additional information and research. Video of each of the hearings is
available from the Clerk
of the Board.
February 9, 2011
During the previous public
hearings on October 20, November 10, and December 8 regarding the
proposed General Plan Update, staff was asked by the Board of
Supervisors to return with additional information regarding specific
identified issues including staff analysis for the 230
property-specific requests that were submitted via verbal or written
testimony or referred to staff by the Board of Supervisors.
March 16, 2011
This staff report contains
responses to questions raised by the Board on February 9, 2011 and
refinements to the previous February 9, 2011 staff report based on
public and staff review.
April 13, 2011
This staff report contains staff’s review of the property owner requests classified as a “moderate” and “major” in the March 16th 2011 staff report, to determine if there are any staff recommendation land use alternatives that would reduce them to “minor” changes.
August 3, 2011
Based on direction from the Board
on April 13, the August 3 documents contain a number of changes to the
General Plan Update that were considered “minor” because they were
consistent with the General Plan Update guiding principles and did not
require recirculation of the Environmental Impact Report. As directed
by the Board, the August 3 report also contains all final documents
necessary to make a decision on the General Plan Update.
January 9, 2012
On Aug. 3, the Board of
Supervisors adopted the General Plan Update. Following adoption of the
plan, the Board voted to schedule a workshop to review the Property
Specific Requests that were submitted during the General Plan Update
hearings but not included in the adopted plan. These requests were
submitted during public testimony on the General Plan Update and
evaluated in the March 16 staff report. Approximately 137 specific
requests were analyzed by staff for the workshop and the analysis is
now available to the public.
June 20, June 27, July 25, and September 12, 2012
During a workshop held January 9 through January 11, 2012, the
Board of Supervisors considered over 137 private property owner
requests to modify the County of San Diego’s General Plan land use
designations. 56 requests were referred back to staff by the Board for
further evaluation. Actions directed by the Board varied between
requests but included steps such as determining if a modified request
was available that could be consistent with the General Plan Guiding
Principles, obtaining community planning group input, determining what
larger study areas (if any) required consideration in making changes
to the plan, notifying potentially affected property owners, and
developing workplan options for amending the General Plan. These
reports respond to Board direction related to the private property
owner requests.