PDS2004-3800-04-003; PDS2004-3810-04-002; PDS2004-3600-04-009; PDS2019-STP-19-033; PDS2004-3100-5361; LOG NO. PDS2004-3910-04-19-005; SCH NO. 2004101058
The Project includes a General Plan Amendment (PDS2004-3800-04-003), a Specific Plan (PDS2004-3810-04-002), a Zone Reclassification (PDS2004-3600-04-009), a Site Plan (PDS2019-STP-19-033), a Tentative Map (PDS2004-3100-5361), LOG NO. PDS2004-3910-04-19-005, SCH NO. 2004101058
The Draft Final Environmental Impact Report (EIR) is now available for review. Any changes to the Draft Final EIR are indicated in strikeout-underline. Technical appendices indicated by an asterisk have been revised since the public review periods.
Please note, the following responses have been updated to include attachments as of 5 PM on April 7, 2020: (A-4, O-14, RO-1, RO-4, RO-6, RO-7, Global Response R1 for 2019 Recirdulation Comments, Global Response R2 for 2019 Recirculation Comments)
Please note, the following technical appendices have been updated as of 5 PM on April 13, 2020 as indicated by two asterisks to include a summary of changes and a tracked changes version of the appendices: (C-2, C-12, D-3, D-16, D-17, D-24)
The Draft Environmental Impact Report (EIR) for the Project was previously circulated for public review from April 3, 2015 to May 22, 2015. Since the original public review period, recirculation of two portions of the Draft EIR was required. The County determined it was necessary to recirculate the Global Climate Change Section, Alternatives Chapter, and Appendices for public review. Comments regarding the Draft EIR circulated from April 3, 2015 to May 22, 2015 as well as this recirculated Draft Revised Global Climate Change Section, Draft Revised Project Alternatives Chapter, and recirculated Appendices are included in the Final EIR.
The project is a mixed-use development of an undevelopmed 1,869 acre site on the southern portion of an area within the 23,000 acre Otay Ranch and is identified as the Proctor Valley Parcel. The land uses proposed by the project include: 1,881 single-family residences on approximately 525 acres, an approximately 14 acre mixed use site that includes 57 multi-family residences and approximately 20,000 square feet of commercial use, approximately 28-acres of park land, an approximately 17 acre resort site with 200 guest rooms and up to 20,000 square feet of commercial office uses, an approximately 2 acre public safety site for a fire station, a 10 acre elementary school site, 144 acres of manufactured open space, 1,089 acres of preserve open space, and 39 acres for roadways.
Project Contact: Greg Mattson | Gregory.Mattson@sdcounty.ca.gov | (858) 694-2249
The County of San Diego (County) is providing information regarding the Draft Final Environmental Impact Report, responses to comments from correspondence received during and after the Planning Commission, responses to comments on Greenhouse Gas Emissions/Protocol Public Disclosure, Appendix E-1 and final MMRP with attachments for the proposed Otay Ranch Resort Village (Village 13). The above noted documents have been posted following the April 17, 2020 Planning Commission Hearing and prior to the November 18, 2020 Board of Supervisors Hearing. These documents are found in the green highlighted heading sections of the website and individually noted by a *** asterisk.
***Draft Final Environmental Impact Report (September 2020, Current)
Documents Revised Since Planning Commission and Public Disclosure Prior to Board of Supervisors Meeting
COVER SHEET, TABLE OF CONTENTS, LIST OF ACRONYMS AND ABBREVIATIONS, SUMMARY
CHAPTER 1.0 PROJECT DESCRIPTION, LOCATION, AND ENVIRONMENTAL SETTING
CHAPTER 2.0 SIGNIFICANT ENVIRONMENTAL EFFECTS
- 2.1 Aesthetics and Visual Resources
- 2.2 Air Quality
- 2.3 Biological Resources
- 2.4 Cultural Resources
- 2.5 Geology and Soils
- 2.6 Hazards and Hazardous Materials
- 2.7 Noise
- 2.8 Solid Waste
- 2.9 Transportation and Traffic
- 2.10 Global Climate Change
CHAPTER 3.0 ENVIRONMENTAL EFFECTS FOUND NOT TO BE SIGNIFICANT
- 3.1 Agricultural Resources
- 3.2 Hydrology and Water Quality
- 3.3 Land Use and Planning
- 3.4 Mineral Resources
- 3.5 Population and Housing
- 3.6 Public Services
- 3.7 Utilities and Service Systems
- 3.8 Energy Use and Conservation
CHAPTER 4.0 PROJECT ALTERNATIVES
CHAPTER 5.0 LIST OF REFERENCES
CHAPTER 6.0 LIST OF EIR PREPARERS AND PERSONS AND ORGANIZATIONS CONTACTED
CHAPTER 7.0 LIST OF MITIGATION MEASURES AND ENVIRONMENTAL DESIGN CONSIDERATIONS
***Additional Documents
Mitigation Monitoring and Reporting Program (MMRP) (Updated November 6, 2020)
***Response to Comments Received During Planning Commission and Public Disclosure Prior to Board of Supervisors Meeting Current
***Comments Received During and After April 17, 2020 Planning Commission Hearing
Responses to Comments Received During and After April 17, 2020 Planning Commission Hearing
PC-1:
United States Fish and Wildlife Service, Carlsband Fish and Wildlife
Service
PC-2:
California Department of Fish and Wildlife
PC-3:
Climate Action Campaign
PC-4:
California Native Plant Society San Diego Chapter
PC-5:
Sierra Club San Diego Chapter
PC-6:
Shute, Mihaly, and Weinberger LLP
PC-7:
Land Protection Partners
Compiled
eComments and General Letters Received
***Comments Received During Public Disclosure Period (August 20, 2020 to September 18, 2020)
1.
California Native Plant Society (9-18-2020)
2.
Endangered Habitats League (9-18-2020)
3.
Lesley Handa (9-17-2020)
4.
Sierra Club (9-18-2020)
ADDITIONAL INFORMATION REGARDING CARBON OFFSET PROTOCOLS FOR GREENHOUSE GAS EMISSION REDUCTION
Public Disclosure Period
(August 20, 2020 to September 18, 2020)
Current
The County of San Diego (County) is providing information regarding the updated mitigation measures for greenhouse gas impacts from the proposed Otay Ranch Resort Village (Village 13) project (proposed Project). The County is providing this information for a 30-day public disclosure period and requesting that the public and interested stakeholders review and provide comment on the carbon offset protocols to be used as mitigation of the proposed Project’s greenhouse gas impacts. Comments must be received by the County no later than September 18, 2020 at 4:00 p.m.
Notice of Additional Information/Legal Ad
1. Mitigation Measures M-GCC-7 and M-GCC-8
2. M-GCC-7 Attachment A – Part 1 of 3 Climate Action Reserve
3. M-GCC-7 Attachment A – Part 2 of 3 American Carbon Registry
4. M-GCC-7 Attachment A – Part 3 of 3 Verra
5. M-GCC-7 Attachment B – Implementation Flowchart
6. Global Response R1 – Carbon Offsets (Updated)
7. Global Response R1 – Carbon Offsets (Track Changes Version)
8. Attachment to Global Response R1
***9. Global Response R2 – Climate Action Plan (Updated) (See Response to Comments on the 2019 Recirculated EIR at the following Link)
***10. Global Response R2 – Climate Action Plan (Track Changes Version) (See Response to Comments on the 2019 Recirculated EIR at the following Link)
Informational Item - The following third-party document was not used as part of the environmental analysis for the project. The document is an operational assessment of fire services prepared for the County Fire Authority by Rohde and Associates.
Draft Final Environmental Impact Report
(April 17, 2020
Planning Commission Hearing)
TABLE OF CONTENTS, LIST OF ACRONYMS AND ABBREVIATIONS
CHAPTER 1.0 PROJECT DESCRIPTION, LOCATION, AND ENVIRONMENTAL SETTING
CHAPTER 2.0 SIGNIFICANT ENVIRONMENTAL EFFECTS
- 2.1 Aesthetics and Visual Resources
- 2.2 Air Quality
- 2.3 Biological Resources
- 2.4 Cultural Resources
- 2.5 Geology and Soils
- 2.6 Hazards and Hazardous Materials
- 2.7 Noise
- 2.8 Solid Waste
- 2.9 Transportation and Traffic
- 2.10 Global Climate Change
CHAPTER 3.0 ENVIRONMENTAL EFFECTS FOUND NOT TO BE SIGNIFICANT
- 3.1 Agricultural Resources
- 3.2 Hydrology and Water Quality
- 3.3 Land Use and Planning
- 3.4 Mineral Resources
- 3.5 Population and Housing
- 3.6 Public Services
- 3.7 Utilities and Service Systems
- 3.8 Energy Use and Conservation
CHAPTER 4.0 PROJECT ALTERNATIVES
CHAPTER 5.0 LIST OF REFERENCES
CHAPTER 6.0 LIST OF EIR PREPARERS AND PERSONS AND ORGANIZATIONS CONTACTED
CHAPTER 7.0 LIST OF MITIGATION MEASURES AND ENVIRONMENTAL DESIGN CONSIDERATIONS
Comments Received on the 2015 DEIR and 2019 Recirculated
DEIR
(As Referenced In DFEIR Dated September 2020)
Current
Comments Received on the 2015 Draft EIR
Global
Response 1 - Phase 2 RMP
Global
Response 2 - Golden Eagle
Global
Response 3-5 Travel Time and Standard Methodology, Fire Service
Provision, Determining Adequacy of Response/NFPA 1710
Federal, State, and Local Agencies
A-1
US Fish and Wildlife Service and CA Fish and Wildlife Service
(Response)
A-2
California Department of Transportation (Response)
A-3
City of San Diego, Attachment
1, Attachment
2 (Response)
A-4
City of Chula Vista (Response)
A-5
Otay Water District, Attachment
(Response)
A-6
San Diego Local Agency Formation Commission (Response)
A-7
City of Chula Vista (Response)
Organizations
O-1
California Native Plant Society San Diego (Response)
O-2
Stephen and Mary Birch Foundation (Response)
O-3
League of Women Voters (Response)
O-4
San Diego County Archaeological Society (Response)
O-5
San Diego Audubon Society (Response)
O-6
Endangered Habitats League (Response)
O-7
Pratt and Ballmer (Response)
O-8
Klein-Edwards Professional Services (Response)
O-9
David Faulkner (Response)
O-10
Dr. Daniel A. Marschalek (Response)
O-11
Ken H. Osborne (Response)
O-12
Preston et al. (Response)
O-13
Stuart B. Weiss (Response)
O-14
Johnson and Sedlack on behalf of the Endangered Habitats League,
Attachments: 1,
2,
3,
4,
5,
6,
7,
8,
9
(Response)
O-15
California Chaparral Institute, Center for Biological Diversity,
Preserve Wild Santee, Attachment
(Response)
O-16
San Diego Trail Alliance (Response)
O-17
Environmental Center of San Diego (Response)
Tribal Organizations
T-1
Rincon Band of Luiseño Indians (Response)
T-2
Soboba Band of Luiseño Indians (Response)
Individuals
Comments Received on the 2019 Recirculated Draft EIR
Global
Response R1 - Carbon Offsets (Attachment)
***Global
Response R2 - County of San Diego Climate Action Plan (Attachment
1, Attachment
2)
Global
Response R3 - Structure Vulnerability and Ignition
Global
Response R4 - Quino Checkerspot Butterfly
Global
Response R5 - Wildfire Protection and Evacuation
Federal, State, and Local Agencies
RA-1
City of San Diego (Response)
RA-2
California Department of Fish and Wildlife (Response)
RA-3
SANDAG (Response)
RA-4
California Department of Transportation (Response)
RA-5
State of California Attorney General (Response)
Organizations
***RO-1
Sierra Club (Response,
Response
Attachment)
***RO-2
California Native Plant Society San Diego (Response)
***RO-3
Southwest Regional Council of Carpenters (Response)
***RO-4
Center for Biological Diversity, California Chaparral Institute,
Preserve Wild Santee, Attachments: 1,
2,
3,
4,
5,
6,
7,
8,
9,
10,
11,
12,
13,
14,
15,
16,
17,
18,
19,
20,
21,
22,
23,
24
(Response)
RO-5
Center for Biological Diversity (Response)
***RO-6
Endangered Habitats League, Attachments: 1,
2,
3,
4,
5,
6,
7,
8,
9,
10,
11,
12,
13,
14,
15,
16,
17,
18,
19,
20,
21,
22,
23,
24,
25,
26,
27,
28,
29,
30,
31,
32,
33,
34,
35,
36,
37
(Response)
RO-7
Save Our Mojave (Response)
RO-8
San Diego Mountain Biking Association (Response)
RO-9
Endangered Habitats League (Response)
TECHNICAL APPENDICES
(As Referenced In DFEIR Dated September
2020)
Current
A - Initial Study and Notice of Preparation
B - General Plan Amendment Report
C-1 - Air Quality Impact Report
Air Quality Impact Report Appendices
*C-2 - Global
Climate Change Evaluation
Global
Climate Change Evaluation Appendices
**C-2-Summary
of Changes
Tracked
Changes of Global Climate Change Evaluation with
Appendices
C-3 - Biological Resources Technical Report
Biological Resources Map
Biological Resources Map with Proposed Development
Footprint
Sensitive Plant Species Map
Sensitive Plant Species Map with Proposed
Development Footprint
Jurisdictional Delineation Map
Jurisdictional Delineation Map with Proposed
Development Footprint
Proposed Fencing, Preserve Signage, and Fuel
Modification Zones with Proposed Footprint
Biological Resources Technical Report Appendices
Part 1, Part 2
C-4 - Archaeological/Historical
Study
Part 1, Part 2, Part 3, Part 4, Part 5, Part 6, Part 7, Part 8, Part 9
C-5 - Paleontological Resource and Monitoring Assessment
C-6 - Area A TM Level Geotechnical Investigation
Area A TM Level Geotechnical Investigation Appendices
C-7 - Area B TM Level Geotechnical
Investigation
Part 1, Part 2, Part 3, Part 4, Part 5, Part 6, Part 7, Part 8, Part 9, Part 10
Area B TM Level Geotechnical Investigation Appendices
C-8 - Otay Lakes Road Widening and Realignment
Geotechnical Investigation
Otay Lakes Road Widening and Realignment
Geotechnical Investigation Appendices
*C-9 - Phase I Environmental Site Assessment
C-10 - Phase I Environmental Site Assessment West
Residential Area Parcels A and B
Addendum 1, Appendices A-G
C-11 - Noise Impact Report
Noise Impact Report Appendices
*C-12 - Traffic
Impact Study
Traffic
Impact Study Appendices
**C-12-Summary
of Changes
Tracked
Changes of Traffic Impact Study
C-13 - Drainage Study
Part 1, Part 2, Part 3, Part 4, Part 5, Part 6, Part 7, Part 8, Part 9, Part 10, Part 11
C-14 - CEQA Preliminary Storm Water
Management Plan
Part 1, Part 2, Part 3, Part 4, Part 5
C-15 - Mineral Resource Evaluation Study
Mineral Resource Evaluation Study Appendices
C-16 - Overview of Sewer Service
Overview of Sewer Service Appendices
C-17 - Overview of Water Service
C-18 - OWD Water Supply Assessment and Verification
Report
OWD Water Supply Assessment and Verification Report Appendices
C-19 - Service Availability Letters
C-20 - Technical Memorandum - Safety Zone Boundaries for
John Nichols's Field
Technical Memorandum - Attachments
C-21 - Fire Protection Plan
Fire Protection Plan Appendices
C-22 - NTSB Accident Report
Part 1, Part 2
C-23 - Preserve Edge Plan
*C-24 - Construction Crushing and Blasting Technical Memorandum
C-25 - Otay Ranch Resort Village GHG Emissions - Alternative B Memorandum
C-26 - AB 900 Project Performance Standards
C-27 - Newhall Ranch Greenhouse Gas Reduction Plan
*C-28 - Salt Creek Interceptor Memo
***C-29 - Attachments A and B for Mitigation Measure M-GCC-7 and M-GCC-8 (Attachment A Part 1, Attachment A Part 2, Attachment A Part 3, Attachment B)
TECHNICAL APPENDICES (ALTERNATIVE H)
*APPENDIX D-1 AIR QUALITY AND GLOBAL CLIMATE CHANGE SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
*APPENDIX
D-3 BIOLOGICAL TECHNICAL REPORT SUPPLEMENTAL ANALYSIS - ALTERNATIVE
H
**APPENDIX
D-3 SUMMARY OF CHANGES
**APPENDIX
D-3 TRACKED CHANGES OF BIOLOGICAL TECHNICAL REPORT SUPPLEMENTAL
ANALYSIS - ALTERNATIVE H
APPENDIX D-4 CULTURAL RESOURCES SURVEY SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-5 PALEONTOLOGICAL RESOURCES SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-6 GEOTECHNICAL INVESTIGATION SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-11 NOISE IMPACT REPORT SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-13 DRAINAGE STUDY - ALTERNATIVE H (NO CHANGES SINCE PUBLIC REVIEW)
APPENDIX D-15 MINERAL RESOURCES SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
*APPENDIX
D-16 OVERVIEW OF SEWER SERVICE SUPPLEMENTAL ANALYSIS - ALTERNATIVE
H
**APPENDIX
D-16 SUMMARY OF CHANGES
**APPENDIX
D-16 TRACKED CHANGES OF OVERVIEW OF SEWER SERVICE SUPPLEMENTAL
ANALYSIS - ALTERNATIVE H
*APPENDIX
D-17 OVERVIEW OF WATER SERVICE SUPPLEMENTAL ANALYSIS - ALTERNATIVE
H
**APPENDIX
D-17 SUMMARY OF CHANGES
**APPENDIX
D-17 TRACKED CHANGES OF OVERVIEW OF WATER SERVICE SUPPLEMENTAL
ANALYSIS - ALTERNATIVE H
*APPENDIX D-21 FIRE PROTECTION PLAN - ALTERNATIVE H
*APPENDIX
D-21A FIRE SAFETY MEMO EVACUATION PLAN
*APPENDIX D-23 PRESERVE PROTECTION PLAN - ALTERNATIVE H
*APPENDIX
D-24 MITIGATION AND MONITORING PROGRAM COMPLIANCE FOR OTAY RANCH
GDP/SRP PROGRAM EIR
**APPENDIX
D-24 SUMMARY OF CHANGES
**APPENDIX
D-24 TRACKED CHANGES OF MITIGATION AND MONITORING PROGRAM COMPLIANCE
FOR OTAY RANCH GDP/SRP PROGRAM EIR
PLANNING DOCUMENTS
(As Referenced In DFEIR Dated September
2020)
Current
TENTATIVE MAP (Area A)
Sheet 1, Sheet 2, Sheet 3, Sheet 4, Sheet 5, Sheet 6, Sheet 7, Sheet 8, Sheet 9, Sheet 10, Sheet 11, Sheet 12, Sheet 13
TENTATIVE MAP (Area B)
Sheet 1, Sheet 2, Sheet 3, Sheet 4, Sheet 5, Sheet 6, Sheet 7, Sheet 8, Sheet 9, Sheet 10, Sheet 11, Sheet 12, Sheet 13, Sheet 14, Sheet 15
SPECIFIC PLAN
SPECIFIC PLAN - Appendix I Preserve Edge
Plan
SPECIFIC PLAN - Appendix II Fire Protection
Plan
SPECIFIC PLAN - Appendix II Fire Protection Plan
Appendices
SPECIFIC PLAN - Appendix III Energy Use
Conservation
SPECIFIC PLAN - Appendix IV Public Facilities
Finance Plan
SPECIFIC PLAN - Appendix IV Public Facilities
Finance Plan Appendices
SPECIFIC PLAN - Appendix V Village Design
Plan
SPECIFIC PLAN - Appendix VI Water Conservation
Plan
SPECIFIC PLAN - Appendix VII Specific Plan Requirements
PLANNING DOCUMENTS (ALTERNATIVE H)
*SPECIFIC PLAN - OTAY RANCH RESORT VILLAGE ALTERNATIVE H
*APPENDIX I PRESERVE EDGE PLAN
*APPENDIX II FIRE PROTECTION PLAN
*APPENDIX III ENERGY CONSERVATION PLAN
*APPENDIX IV PUBLIC FACILITIES AND FINANCING PLAN, FISCAL IMPACT ANALYSIS
*APPENDIX V OTAY RANCH RESORT VILLAGE ALTERNATIVE H RESORT VILLAGE DESIGN PLAN PART 1
*APPENDIX V OTAY RANCH RESORT VILLAGE ALTERNATIVE H RESORT VILLAGE DESIGN PLAN PART 2
*APPENDIX VI WATER CONSERVATION PLAN
*APPENDIX VII INDEX OF SPECIFIC PLAN REQUIREMENTS
***APPENDIX E-1 GENERAL PLAN AMENDMENT REPORT
***APPENDIX E-1 GENERAL PLAN AMENDMENT REPORT - ATTACHMENT A
Due to the additions and changes made to the Draft EIR, the County has decided to recirculate two revised portions of the Draft EIR for the proposed project. These two portions are the Project Alternatives Chapter 4.0 which introduces a new project-level alternative (Alternative H) and the Draft Revised Global Climate Change Section 2.10. Pursuant to CEQA Guidelines Section 15088.5(f)(2), reviewers should limit their comments to the revised Chapter 4.0, new Alternative H Appendices, Section 2.10 and associated climate change appendices below, of the recirculated EIR only.
For ease of review, the County has included the entirety of Section 2.10 and Appendix C-2 for the DEIR in a clean format (no strikeout/underline) because they wholly replace the previous Section 3.8 and Appendix C-2. The entirety of Chapter 4 is also provided in a clean format (no strikeout/underline). The Alternative H Technical Appendices and Planning Documents are also provided.
Comments on the recirculated Draft Revised EIR must be received no later than May 28, 2019 at 4:00 P.M. (45-day public review period). Please refer to the Readers Guide and Recirculation Findings below for further clarifications.
A. RECIRCULATED CHANGES TO DRAFT EIR
SECTION 2.10 GLOBAL CLIMATE CHANGE
CHAPTER 4 PROJECT ALTERNATIVES
APPENDICES
APPENDIX C-2 CLIMATE CHANGE EVALUATION FOR THE OTAY RANCH RESORT VILLAGE 13
APPENDIX C-2 CLIMATE CHANGE EVALUATION FOR THE OTAY RANCH RESORT VILLAGE 13 APPENDICES
APPENDIX C-25 GREENHOUSE GAS EMISSIONS ANALYSIS ALTERNATIVE B MEMORANDUM
B. TECHNICAL APPENDICES (ALTERNATIVE H)
APPENDIX D-1 AIR QUALITY AND GLOBAL CLIMATE CHANGE SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-3 BIOLOGICAL TECHNICAL REPORT SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX A - FOCUSED QUINO CHECKERSPOT BUTTERFLY
APPENDIX B - VERNAL POOL MITIGATION PLAN
APPENDIX C - QUINO CHECKERSPOT BUTTERFLY MANAGEMENT/ENHANCEMENT PLAN
APPENDIX D-4 CULTURAL RESOURCES SURVEY SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-5 PALEONTOLOGICAL RESOURCES SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-6 GEOTECHNICAL INVESTIGATION SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-11 NOISE IMPACT REPORT SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-12 TRAFFIC IMPACT STUDY SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-13 DRAINAGE STUDY - ALTERNATIVE H
APPENDIX D-14 CEQA PRELIMINARY STORMWATER MANAGEMENT PLAN - ALTERNATIVE H
APPENDIX D-15 MINERAL RESOURCES SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-16 OVERVIEW OF SEWER SERVICE SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-17 OVERVIEW OF WATER SERVICE SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-18 WATER SUPPLY ASSESSMENT AND VERIFICATION REPORT - ALTERNATIVE H
APPENDIX D-19 SERVICE AVAILABILITY LETTERS SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-20 HAZARDS TECHNICAL MEMO SUPPLEMENTAL ANALYSIS - ALTERNATIVE H
APPENDIX D-21 FIRE PROTECTION PLAN - ALTERNATIVE H
APPENDIX D-23 PRESERVE PROTECTION PLAN - ALTERNATIVE H
APPENDIX D-24 MITIGATION AND MONITORING PROGRAM COMPLIANCE FOR OTAY RANCH GDP/SRP PROGRAM EIR
C. PLANNING DOCUMENTS (ALTERNATIVE H)
SPECIFIC PLAN - OTAY RANCH RESORT VILLAGE ALTERNATIVE H
APPENDIX II FIRE PROTECTION PLAN
APPENDIX III ENERGY CONSERVATION PLAN
APPENDIX IV PUBLIC FACILITIES AND FINANCING PLAN, FISCAL IMPACT ANALYSIS
APPENDIX V OTAY RANCH RESORT VILLAGE ALTERNATIVE H RESORT VILLAGE DESIGN PLAN
APPENDIX VI WATER CONSERVATION PLAN
APPENDIX VII INDEX OF SPECIFIC PLAN REQUIREMENTS
APPENDIX E-1 GENERAL PLAN AMENDMENT REPORT
APPENDIX E-1 GENERAL PLAN AMENDMENT REPORT - ATTACHMENT A
Draft Environmental Impact Report, Appendices, and Project
Documents
(Public Review Period April 3,
2015 to May 22, 2015)
Click Here for the Recirclated Draft Environmental Impact Report
PROJECT DOCUMENTS
Legal
Ad
Aerial
Overview of Project Site
Regional
Location and Project Vicinity Aerial Photo
USGS Map
TENTATIVE MAP (Area A)
Sheet 1, Sheet 2, Sheet 3, Sheet 4, Sheet 5, Sheet 6, Sheet 7, Sheet 8, Sheet 9, Sheet 10, Sheet 11, Sheet 12, Sheet 13
TENTATIVE MAP (Area B)
Sheet 1, Sheet 2, Sheet 3, Sheet 4, Sheet 5, Sheet 6, Sheet 7, Sheet 8, Sheet 9, Sheet 10, Sheet 11, Sheet 12, Sheet 13, Sheet 14, Sheet 15
SPECIFIC PLAN
SPECIFIC PLAN - Appendix I Preserve Edge
Plan
SPECIFIC PLAN - Appendix II Fire Protection
Plan
SPECIFIC PLAN - Appendix II Fire Protection Plan
Appendices
SPECIFIC PLAN - Appendix III Energy Use
Conservation
SPECIFIC PLAN - Appendix IV Public Facilities
Finance Plan
SPECIFIC PLAN - Appendix IV Public Facilities
Finance Plan Appendices
SPECIFIC PLAN - Appendix V Village Design
Plan
SPECIFIC PLAN - Appendix VI Water Conservation
Plan
SPECIFIC PLAN - Appendix VII Specific Plan Requirements
OTAY RANCH PHASE 2 RESOURCE MANAGEMENT PLAN
ENVIRONMENTAL DOCUMENTS
Draft Environmental Impact Report
TABLE OF CONTENTS, LIST OF ACRONYMS AND
ABBREVIATIONS
SUMMARY
CHAPTER 1.0 PROJECT DESCRIPTION, LOCATION, AND ENVIRONMENTAL SETTING
CHAPTER 2.0 SIGNIFICANT ENVIRONMENTAL EFFECTS
- 2.1 Aesthetics and Visual Resources
- 2.2 Air Quality
- 2.3 Biological Resources
- 2.4 Cultural Resources
- 2.5 Geology and Soils
- 2.6 Hazards and Hazardous Materials
- 2.7 Noise
- 2.8 Solid Waste
- 2.9 Transportation and Traffic
CHAPTER 3.0 ENVIRONMENTAL EFFECTS FOUND NOT TO BE SIGNIFICANT
- 3.1 Agricultural Resources
- 3.2 Hydrology and Water Quality
- 3.3 Land Use and Planning
- 3.4 Mineral Resources
- 3.5 Population and Housing
- 3.6 Public Services
- 3.7 Utilities and Service Systems
- 3.8 Climate Change
- 3.9 Energy Use and Conservation
CHAPTER 4.0 PROJECT ALTERNATIVES
CHAPTER 5.0 LIST OF REFERENCES
CHAPTER 6.0 LIST OF EIR PREPARERS AND PERSONS AND ORGANIZATIONS CONTACTED
CHAPTER 7.0 LIST OF MITIGATION MEASURES AND ENVIRONMENTAL DESIGN
CONSIDERATIONS
Technical Appendices
A - Initial Study and Notice of Preparation
B - General Plan Amendment Report
C-1 - Air Quality Impact Report
Air Quality Impact Report Appendices
C-2 - Global Climate Change Evaluation
Global Climate Change Evaluation Appendices
C-3 - Biological Resources Technical Report
Biological Resources Map
Biological Resources Map with Proposed Development
Footprint
Sensitive Plant Species Map
Sensitive Plant Species Map with Proposed
Development Footprint
Jurisdictional Delineation Map
Jurisdictional Delineation Map with Proposed
Development Footprint
Proposed Fencing, Preserve Signage, and Fuel
Modification Zones with Proposed Footprint
Biological Resources Technical Report Appendices
Part 1, Part 2
C-4 - Archaeological/Historical
Study
Part 1, Part 2, Part 3, Part 4, Part 5, Part 6, Part 7, Part 8, Part 9
C-5 - Paleontological Resource and Monitoring Assessment
C-6 - Area A TM Level Geotechnical Investigation
Area A TM Level Geotechnical Investigation Appendices
C-7 - Area B TM Level Geotechnical
Investigation
Part 1, Part 2, Part 3, Part 4, Part 5, Part 6, Part 7, Part 8, Part 9, Part 10
Area B TM Level Geotechnical Investigation Appendices
C-8 - Otay Lakes Road Widening and Realignment
Geotechnical Investigation
Otay Lakes Road Widening and Realignment
Geotechnical Investigation Appendices
C-9 - Phase I Environmental Site Assessment
Appendix A, Appendix B, Appendix C-Part-1, Appendix C-Part-2, Appendix D, Appendix E, Appendix F, Appendix G-Part-1, Appendix G-Part-2, Appendix H
C-10 - Phase I Environmental Site Assessment West
Residential Area Parcels A and B
Addendum 1, Appendices A-G
C-11 - Noise Impact Report
Noise Impact Report Appendices
C-12 - Traffic Impact Study
Traffic Impact Study Appendices
C-13 - Drainage Study
Part 1, Part 2, Part 3, Part 4, Part 5, Part 6, Part 7, Part 8, Part 9, Part 10, Part 11
C-14 - CEQA Preliminary Storm Water
Management Plan
Part 1, Part 2, Part 3, Part 4, Part 5
C-15 - Mineral Resource Evaluation Study
Mineral Resource Evaluation Study Appendices
C-16 - Overview of Sewer Service
Overview of Sewer Service Appendices
C-17 - Overview of Water Service
C-18 - OWD Water Supply Assessment and Verification
Report
OWD Water Supply Assessment and Verification Report Appendices
C-19 - Service Availability Letters
C-20 - Technical Memorandum - Safety Zone Boundaries for
John Nichols's Field
Technical Memorandum - Attachments
C-21 - Fire Protection Plan
Fire Protection Plan Appendices
C-22 - NTSB Accident Report
Part 1, Part 2
C-23 - Preserve Edge Plan