Fallbrook Sub-Area Plan
Project Contact: Timothy Vertino | PDS.LongRangePlanning@sdcounty.ca.gov | (858) 505-6677
To sign up for updates on the project, please Click Here.
Project Updates | October 2024
The County of San Diego Planning Commission recommended approval of
the Fallbrook Sub-Area Plan on Friday, September 20, 2024. Please see
“Draft Sub-Area Plan” below to review the project materials.
Planning Commission Hearing
On September 20, 2024, the County of San Diego Planning Commission recommended that the Board of Supervisors accept the Fallbrook Sub-Area Plan. Please review the Planning Commission Staff Report for more information.
Draft Sub-Area Plan
The Draft Plan is the result of a collaborative effort between the community, various stakeholders, and County groups. The Draft Plan supports revitalization and beautification efforts for the Fallbrook downtown area. These efforts are intended to attract and retain residents, businesses, and tourism, as well as improve pedestrian access and mobility.
The Draft Plan consists of three main components:
- Fallbrook Village Zoning Ordinance Amendments
- Updates to the Fallbrook Design Guidelines
- Streetscape Plan for Main Avenue
The Plan also includes the rezone of a surface parking lot from S86 (Parking) zoning to Fallbrook Village 1 zoning to allow for future mixed-use development.
You can review the Draft Plan by following the link below:
Revised Draft Fallbrook Sub-Area Plan (March 2024)
First Draft Fallbrook Sub-Area Plan
Supporting Technical Appendices
- Appendix A: Phase 1 Downtown Visioning Report (March 2024)
- Appendix B: Community Engagement Summary (March 2024)
- Appendix C: Market Profile Report (March 2024)
- Appendix D: Mobility Report (March 2024)
- Appendix E: Parking Report (March 2024)
- Appendix F: Zoning Amendments March 2024 (Clean)
- Appendix F2: Zoning Amendments March 2024 (Tracked Changes)
- Appendix G: Design Standards September 2024 (Clean)
- Appendix H: Streetscape Plan March 2024 (Large)
Project Timeline
Item | Timeline | Status |
Public Review of Draft Sub-Area Plan and Community Engagement | October 20 – December 22 2023 | Complete |
Review Public Input Received & Potential Revisions | Winter 23 – Spring 24 | Complete |
2nd Public Review of Revised Draft Sub-Area Plan | Spring - Summer 2024 | Complete |
Fallbrook Community Planning Group Meeting | August 19, 2024 | Complete |
Planning Commission Hearing | September 20, 2024 | Complete |
Board of Supervisors Hearing | Winter 2024 | Upcoming |
Project Background
In 2019, the County Board of Supervisors allocated $900,000 for
development of a Fallbrook Form Based Code, and County Supervisor Jim
Desmond (D5) initiated the coordination with community members
representing a range of interests and Planning & Development
Services to discuss a Fallbrook Form Based Code.
The project's boundary is roughly defined as View Street - North, Brandon Street - East, Fallbrook Street - South, Mission Road - West.
Phase 1 - Fallbrook Visioning
Planning & Development Services held seven (7) meetings from November 2019 to September 2020 to engage stakeholders on issues and opportunities and scope the future project. Please see the Visioning Report for a summary of these meetings.
On September 21, 2020, the Fallbrook Community Planning Group voted unanimously for Option 2 (Zoning Ordinance & Design Guideline Update with Streetscape Plan). This vote moved the project into Phase 2 - Project Development.
Phase 2 - Existing Conditions
From June 2021, to February 2023, county staff engaged stakeholders on Phase 2 - Existing Conditions. Phase 2 of the process involved initiating the planning process among the project team and community outreach and engagement efforts that contributed to the initial technical planning.
Phase 3 - Draft Plan
The Design Guidelines, Appendix G, was revised per stakeholder input. Appendix G: Design Guidelines Revised August 2024 incorporates feedback received from the public input period.
The revised Draft Plan incorporates changes derived from stakeholder and community comments received after the initial Draft Plan release. Comments on the revised Draft Plan were be accepted until April 12, 2024.
The Draft Plan was available for public input from October 20
through December 22, 2023. A second public input period was held from
March 29 through April 12, 2024.
Fallbrook Documents
Past Stakeholder Engagement
February 20, 2024, Fallbrook Community Planning Group Meeting
December 5, 2023,
Fallbrook CPG/Community Workshop
- See November 15th DRB Meeting below for full staff presentation
November 29, 2023, District 5 Fallbrook Revitalization Meeting
November 15, 2023, Fallbrook Design Review Board Meeting
July 17, 2023, Fallbrook CPG Meeting
February 15, 2023, Fallbrook Design Review Board
December 12, 2022, Fallbrook Infrastructure Committee #5
October 25, 2022, Fallbrook Infrastructure Committee #4
May 11, 2022, Fallbrook Design Review Board
April 6, 2022, Fallbrook Design Review Board
March 16, 2022, Fallbrook Design Review Board
February 15, 2022, Fallbrook Circulation Sub-Committee
February 16, 2022, Fallbrook Design Review Board
February 16, 2022, Parks & Recreation Sub-Committee
January 25, 2022, Fallbrook Infrastructure Committee Meeting #3
December 8, 2021, Infrastructure Committee Meeting #2
November 4, 2021, Equity Focus Group Meeting
September 22, 2021, Community Workshop #1